1.12 Calendar Maintenance(01151m)
A Muli calendar provides the basis for determining the normal working days on a project. Calendars exist for each different day-count basis for each of the Australian States & Territories plus Hong Kong. The standard calendars supplied in a new installation include ACT 5 day, QLD 5 day, HK 5 day, etc.
These calendars provide a relevant basis for calculating key times within Muli such as:
- Variation (Extension of Time)
- Project Scheduling
- Time Sheet Maintenance Background colour
So if we are calculating Concrete Curing, use Calendar 100 - which is a 7 day calendar.
For a normal 5-day Working contract in NSW, use Calendar 102; and if the contract called for a 6-day week, 202 would be applicable as Saturday would be a working day.