4.1 Purchase Order Creation (04200m)
The creation of a Purchase Order initiates the start of the "Commitment phase", by creating an obligation for the company to pay for goods.
If the company requires work to be performed that involves any on-site labour, supplied equipment or ongoing obligations then instead of a Purchase Order, a formal Subcontract should be used. (Refer to Menu 11)
Note: if the "Authority to commit" is authorised for the selected project and Purchase Orders are approved, then they will displayed for selection (if desired) at field #3.
- Project
- Allocation
- Order
- Stage
- Order Package
- Supplier
- Currency 223
- Allocated Budget
- Committed Value
- Risk Provided Value
- Order Date
- Projected Start Date
- Projected Finish Date
- Terms 281
- Retention 282
- Accounts Processing RPC
- Template id
- Scope of Order 210
- Create a new document - Yes/No. If you select NO then a Purchase Order number will still be generated but no Document prepared so you can never print it out if you needed to at any time. By selecting YES you will generate a PO number and prepare a document for printing - you still have a choice as to whether you print it our or not. If you entered the PO creation program by selecting F10 from the Accounst Payable Invoice entry secreen (5.1) then you would most likely respond NO.
- Template Questions
- Signature Block
- Exclude values from document - Yes/No