7.3.1.27 Risk2do Timings Scheduling (07711m)

Provision is made to enable the inclusion of Risk2Do items into the project schedule, including the recording of "Standard of Work" achieved on items.  At this time, dates are manually entered.

Risk2do Timings & Scheduling

  1. Start Date
  2. Finish Date
  3. Percentage of complete
  4. Work std 413
  5. Follow on 414
  6. Scheduling Dependencies
  7. Group 452
  8. Duration (days)
  9. Calendar 451
  10. Early Start - The earlest time a activity can start, based on when all preceding activities are completed.
  11. Early Finish - A Scheduling term obtained by working through all the dependencies on a project and assuming they are completed without using any float time when would the ascivity finish
  12. Allocation
  13. Hold until percentage complete