11.5 Subcontract Creation/Adjustment (11330)
All work that involves site labour and/or equipment and/or design work should be executed under a Subcontract, not a Purchase Order.
The Subcontract type (Terms & Conditions) needs to be chosen carefully and normally is related to the Head Contract document.
Muli's approach is to generate an overall management document that links in the relevant Subcontract provided documents that may include:-
- Applicable Subcontract
- Site specific Terms & Conditions
- Company Health & Safety requirements
- Scope of Work (may include Bill of Quantities)
- Specifications
- Drawings
- Extract of the Variable Schedule of the Subcontract and the agreed values
In terms of business risk and correct detailed management, the subcontract process will provide the greatest returns.
As part of the setup process, Muli has set up a number of documents that are in common use, but remember we are a software organisation and do not warrant the legal applicability of provided documents.
Users should confirm that the Muli created document is correct for their usage.
- Project
- Allocation
- Order
- Stage
- Order Package
- Supplier
- Currency 223
This may be turned off. If the currency is not the Default currency, then the proposed currency of the Order will need to be set up in [8.10.1]. - Allocated Budget
- Committed Value - (remember the committed Order value excludes GST)
- Risk Provided Value
- Order Date
- Projected Start Date
- Projected Finish Date
- Terms 281
- Retention 282
- Accounts Processing RPC
- Template ID
- Scope of Order 210
- Create a new document - Yes/No
- Template Questions
- Signature Block
- Exclude values from document - Yes/No